Program Controls
Program report builder is collapsed.
Behind by 136 day(s) versus planned curve at current status
- 1Project Start
- 2Project Completion
COST CURVE
PROGRESS OVERVIEW
Actual 59.7% vs Planned 22.3%
Progress Variance: 37.3%
Ahead/Behind: Behind 136 day(s)
BASELINE VS ACTUAL
BAC: $18,450,000
PV: $4,121,859
EV: $11,020,500
AC: $11,004,512
CV (EV - AC): $15,988
SV (EV - PV): $6,898,641
projAI Project Controls Dashboard
Current Milestone Date: 2027-05-26
Free mode: baseline + auto-generated controls only. Upgrade with card payment to unlock AI chat, reporting, schedule updates, and advanced controls.
CONTROLS ASSURANCE
Evidence-backed command view for schedule quality, data confidence, and owner actions.
Schedule Quality Checks
Action Register
PROJECT HIGHLIGHTS
Stage Update 1 is active. Progress 59.7% vs plan 22.3%. CV $15,988 (favourable) and SV $6,898,641 (ahead/on plan).
Critical Activities - Current Week
- 2. Design, BC, Authority Approvals (2026-05-01 to 2026-07-10, 86% complete, 14 point progress gap): close blockers this week and confirm owner commitments. Owner: Project Controls Lead (Project Controls Lead)
- 3. Site Works & Earthworks (2026-06-05 to 2026-08-29, 74% complete): close blockers this week and confirm owner commitments. Owner: Project Controls Lead (Project Controls Lead)
- 4. Procurement & Long-Lead Items (2026-06-20 to 2026-09-28, 69% complete): close blockers this week and confirm owner commitments. Owner: Project Controls Lead (Project Controls Lead)
- Status snapshot: Update 1 (update). Owner: Project Controls Lead (Project Controls Lead)
- Stage concern: 2. Design, BC, Authority Approvals is 14 points behind expected progress at 86% complete. Action: resolve constraints, resequence interfaces, and verify recovery in the next update. Owner: Project Controls Lead (Project Controls Lead)
- Schedule update cadence is stale (139 days since loaded stage). Owner: Project Controls Lead (Project Controls Lead)
Critical Activities - Next Week
- 3. Site Works & Earthworks (2026-06-05 to 2026-08-29, 74%): prepare next-week work packs, constraints, inspections, and material readiness. Owner: Project Controls Lead (Project Controls Lead)
- 4. Procurement & Long-Lead Items (2026-06-20 to 2026-09-28, 69%): prepare next-week work packs, constraints, inspections, and material readiness. Owner: Project Controls Lead (Project Controls Lead)
- 5. Foundations & Substructure (2026-08-01 to 2026-11-07, 61%): prepare next-week work packs, constraints, inspections, and material readiness. Owner: Project Controls Lead (Project Controls Lead)
- 2. Design, BC, Authority Approvals (2026-05-01 to 2026-07-10, 86%): Week 1: Prepare submission bundle this week and secure authority review windows in advance. Owner: Project Controls Lead (Project Controls Lead)
- 5. Foundations & Substructure (2026-08-01 to 2026-11-07, 61%): Week 2: Break into weekly work packs, assign accountable owner, and track close-out in daily standups. Owner: Project Controls Lead (Project Controls Lead)
- 4. Procurement & Long-Lead Items (2026-06-20 to 2026-09-28, 69%): Week 3: Release procurement package now, lock vendor commitments, and run daily expediting. Owner: Project Controls Lead (Project Controls Lead)
AREAS OF CONCERN & RECOMMENDATIONS
Stage concern: 2. Design, BC, Authority Approvals is 14 points behind expected progress at 86% complete. Action: resolve constraints, resequence interfaces, and verify recovery in the next update. Owner: Project Controls Lead (Project Controls Lead)
High Schedule: Schedule update cadence is stale (139 days since loaded stage). Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Re-baseline near-critical sequence, remove interface constraints, and lock weekly recovery actions with accountable owners. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Medium Delivery / Interface: 1 activity(ies) are overdue (10.0% of loaded tasks). Trigger: scope, baseline, update, and governance evidence. Action: Assign owner, define due date, and track mitigation progress in weekly/monthly controls cycle. Verification: Track owner closeout evidence in the next controls review. Owner: Project Controls Lead (Project Controls Lead)
Medium Schedule: Staff Accommodation Block A has 6 listed scope item(s); predictive controls must track risk and progress at scope-item level, not only at total project level, otherwise Block/package-specific delays can be hidden until handover. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Re-baseline near-critical sequence, remove interface constraints, and lock weekly recovery actions with accountable owners. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Medium Design / Approvals: Staff Accommodation Block A external/services scope item ", bulk earthworks, and underground services diversions." can constrain occupation; drainage, sewer/water connections, access paths, car parking, and external lighting must be complete enough for safe resident access and authority sign-off. Trigger: scope, baseline, update, and governance evidence. Action: Freeze the approval constraint register, assign authority/document owners, and escalate aged decisions through weekly governance. Verification: Track owner closeout evidence in the next controls review. Owner: Project Controls Lead (Project Controls Lead)
Medium Schedule: Staff Accommodation Block A closeout scope item "in, fitout, integrated systems testing, and commissioning." is a documentation risk; inspection records, commissioning sheets, as-builts, O&M manuals, warranties, and occupancy evidence need progressive compilation rather than end-of-job recovery. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Re-baseline near-critical sequence, remove interface constraints, and lock weekly recovery actions with accountable owners. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
RISKS & OPPORTUNITIES
MANPOWER HISTOGRAM
Total manpower: cumulative manpower shortage is 9,659 person-hours across the visible period. Add targeted crews to the red months, resequence blocked work fronts, and protect critical-path activities before adding broad labour.
RISKS & OPPORTUNITIES
Opportunity Schedule: Stage opportunity: protect 3. Site Works & Earthworks (2026-06-05 to 2026-08-29) with early approvals, material checks, and handover gates so current float is not consumed. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Confirm implementation owner, timebox pilot on target package, track realized benefit in weekly controls review. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Opportunity Schedule: Stage opportunity: protect 4. Procurement & Long-Lead Items (2026-06-20 to 2026-09-28) with early approvals, material checks, and handover gates so current float is not consumed. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Confirm implementation owner, timebox pilot on target package, track realized benefit in weekly controls review. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Opportunity Schedule: Stage opportunity: protect 5. Foundations & Substructure (2026-08-01 to 2026-11-07) with early approvals, material checks, and handover gates so current float is not consumed. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Confirm implementation owner, timebox pilot on target package, track realized benefit in weekly controls review. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Medium Delivery / Interface: Enforce monthly update cadence with status-date freeze and evidence cutoff before governance meeting. Trigger: scope, baseline, update, and governance evidence. Action: Assign owner, define due date, and track mitigation progress in weekly/monthly controls cycle. Verification: Track owner closeout evidence in the next controls review. Owner: Project Controls Lead (Project Controls Lead)
Medium Schedule: Run short-interval control on delayed packages: 48-hour blocker closure, daily owner commitments, and weekly PPC review. Trigger: baseline/update variance, float pressure, and activity progress movement. Action: Re-baseline near-critical sequence, remove interface constraints, and lock weekly recovery actions with accountable owners. Verification: Check recovery path in next schedule update and confirm SPI/float movement. Owner: Project Controls Lead (Project Controls Lead)
Opportunity Design / Approvals: Opportunity: separate authority/service connection readiness for ", bulk earthworks, and underground services diversions." from internal room completion so occupation constraints are cleared in parallel with fit-out. Trigger: scope, baseline, update, and governance evidence. Action: Confirm implementation owner, timebox pilot on target package, track realized benefit in weekly controls review. Verification: Track owner closeout evidence in the next controls review. Owner: Project Controls Lead (Project Controls Lead)
HSE HIGHLIGHTS
COST OVERVIEW
Monthly Actual: $11,004,512
Monthly Actual (Current): $11,004,512
Monthly Planned: $18,450,000
Weekly Actual: $2,751,128
FINANCIAL STATUS
SPI: N/A CPI: N/A TCPI: N/A
CV: $15,988 SV: $6,898,641
Budget Utilization: 59.6%
HSE incidents: 0
WBS PACKAGE BREAKDOWN
Add WBS packages in Data Entry to see breakdown.
MANPOWER HISTOGRAM
Monthly Total: 88
Monthly Supervisors: 1
Weekly Manpower: 352
QA / QC STATISTICS
3 activities trailing planned progress.