Project Health
Project Sunshine
Progress 61.6%
CPI 0.94 | SPI 0.91
EAC $142.8M | ETC $57.9M
Project Sunshine
Progress 61.6%
CPI 0.94 | SPI 0.91
EAC $142.8M | ETC $57.9M
Control action: recover long-lead package slippage through resequencing, interface freeze, and owner checkpointing.
Project: Project Sunshine
Status: Behind baseline on selected packages with controlled recovery pathways.
Top action: Accelerate long-lead closeout and protect commissioning float.
Owner: Project Controls Lead | Review: Monthly management cycle
| Package | Baseline Finish | Update Finish | Delta | Action Owner |
|---|---|---|---|---|
| Envelope Package | 2027-01-12 | 2027-01-21 | +9 days | Planner / Controls Lead |
| MEP Interface Zone C | 2027-02-03 | 2027-02-11 | +8 days | Construction Manager |
| Commissioning Readiness | 2027-04-07 | 2027-04-12 | +5 days | Project Manager |